Map Detail

Print
Press Enter to show all options, press Tab go to next option

Project Description

This project includes the grading and paving of SW Vintage Parkway from 1,000 feet east of SW Irvinedale Drive to 200 feet west of SW Magazine Road and utility improvements. 

SW Vintage Pkwy Connection - Project Location Map

Anticipated Start Date

Spring 2016

Expected Completion Date

Spring 2017

Progress Update

There are tree plantings that will be completed this Fall under traffic with possible inside or outside lane closures. -- updated 9/18/17 

The contractor has reached final completion of this project.  There are some additional construction items associated with this project, but are being completed by others.  These are minor construction items and will be completed under traffic with possible inside or outside lane closures, like street light installation, final surface restoration and tree planting.  These items are going to occur during the summer and fall. -- updated 7/11/17 

The contractor has completed the majority of the construction work associated with this project, with the exception of some punch list items for final completion.  There are some additional construction items associated with this project, but are being completed by others.  These are minor construction items and will be completed under traffic with possible inside or outside lane closures, like street light installation, final surface restoration and tree planting.  These items are going to occur during the summer and fall. -- updated 6/13/17 

The final paving has been completed for this project with some final items being wrapped up and an anticipated street opening the week of May 22.  There will be some minor construction items left to complete after the street is opened to traffic, like street light installation, final surface restoration and tree planting.  These items are going to occur under traffic during this coming summer and fall. -- updated 5/23/17 

The final paving has been completed for this project with some final items being wrapped up and an anticipated street opening the first week of June.  There will be some minor construction items left to complete after the street is opened to traffic, like street light installation, final surface restoration and tree planting.  These items are going to occur under traffic during this coming summer and fall. -- updated 5/9/17 

The final paving of the connection between the east and west sides will be completed in Spring 2017 along with the rest of the work on the project. -- updated 3/1/17 

The Contractor has completed most of the underground utilities, including a section of the sanitary sewer that had some issues.  The Contractor has also paved some portions of the street on either side of the sanitary sewer that was fixed.  The final paving of the connection between the east and west sides will not be completed until next spring along with the rest of the work on the project. -- updated 12/6/16 

The Contractor has completed most of the underground utilities, except a section of the sanitary sewer that has some issues and is in the process of being fixed.  The Contractor has also paved some portions of the street on either side of the sanitary sewer to be fixed.  The final paving of the connection between the east and west wide will not be completed until next spring. -- updated 11/8/16 

The Contractor has completed most of the underground utilities, except a section of the sanitary sewer that has some issues and is in the process of being fixed.  The Contractor is also planning on starting the paving work for this project the week of Oct. 10. -- updated 10/11/16 

The contractor has mostly finished the sanitary sewer with a few spot repairs still left to finish.  They are currently working on storm sewer and water main components of the project that won’t be affected by the sanitary sewer spot repairs. -- updated 8/17/16

The contractor has essentially wrapped up the sanitary sewer and is currently working on the storm sewer and water system work. -- updated 7/28/16 

The contractor is wrapping up the sanitary sewer and has started the storm sewer and water system work. -- updated 7/12/16 

The contractor is wrapping up the sanitary sewer and will be starting the storm sewer and water system work in the next week. -- updated 7/6/16 

The contractor is currently working on sanitary sewer installation. -- updated 6/14/16 

The contractor has been working on earthwork and grading and is getting started on sanitary sewer construction. -- updated 5/17/16 

The contractor is scheduled to start construction in early May with earthwork and grading. -- updated 5/3/16 

The contractor is scheduled to start construction in late April with earthwork and grading. -- updated 4/6/16 

This project has been awarded and the contractor is excepted to start construction in early April.  -- updated 3/7/16

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer