Project Description

This project consists of the reconstruction of NE 36th St from just east of N Ankeny Blvd/US Hwy 69 to just west of NE Delaware Ave.  A new traffic signal will be installed at the intersection of NE 36th St and NE Trilein Dr, and a wetland and water quality basin will be constructed south of the Outdoor Education Center.

NE 36th Street Reconstruction-Phase 2 - Project Location Map

NE 36th Street Reconstruction-Phase 2 - FAQ's

NE 36th Street Reconstruction-Phase 2 - Detour Map

NE 36th Street Reconstruction-Phase 2 - Exhibit

 

Anticipated Start Date

March 20, 2017

Expected Completion Date

Fall 2017

Progress Update

NE 36th Street between North Ankeny Boulevard (U.S. Highway 69) and NE Delaware Avenue is now open to traffic. The four-lane arterial street with dedicated left turn lanes and raised medians provides increased traffic capacity and mobility, along with improving safety for both motorists and pedestrians. There is a new traffic signal in service at the intersection of NE 36th Street and NE Trilein Drive, and the speed limit along the NE 36th Street corridor has been lowered from 45 mph to 35 mph. In addition, there is now an 8’ wide sidewalk connection on the north side along the entire corridor.

The City of Ankeny encourages motorists and pedestrians to be aware of intermittent lane closures during the month of October while MidAmerican Energy finishes the installation of the streetlights.  In addition, the street right-of-way will be landscaped with street trees this Fall and ornamental grasses next Spring.  The final surface restoration of the corridor with permanent seeding will be completed in late Spring 2018, once all of the landscaping is completed. -- updated 10/2/17

Paving of NE 36th Street between Fourmile Creek and NE Delaware Avenue is completed.  The intersection of NE 36th Street and NE Briarwood Drive is open to north/south traffic.  Paving of driveways and sidewalks along NE 36th Street between N Ankeny Boulevard and Fourmile Creek will occur during the last half of September.  NE 36th Street will not be open to west/east traffic until the entire corridor from N Ankeny Boulevard to NE Delaware Avenue is completed.  It is anticipated that the corridor will reopen to traffic during the first half of October, weather permitting. -- updated 9/25/17 

Paving of NE 36th Street between Fourmile Creek and NE Delaware Avenue is completed.  The intersection of NE 36th Street and NE Briarwood Drive is open to north/south traffic.  Paving of driveways and sidewalks along NE 36th Street between N Ankeny Boulevard and Fourmile Creek will occur during the last half of September.  NE 36th Street will not be open to west/east traffic until the entire corridor from N Ankeny Boulevard to NE Delaware Avenue is completed.  It is anticipated that the corridor will reopen to traffic in early October, weather permitting. -- updated 9/18/17 

Paving of NE 36th Street between Fourmile Creek and NE Delaware Avenue is completed.  The intersection of NE 36th Street and NE Briarwood Drive is open to north/south traffic.  Paving of NE 36th Street between N Ankeny Boulevard and Fourmile Creek is ongoing over the next few weeks.  NE 36th Street will not be open to west/east traffic until the entire corridor from N Ankeny Boulevard to NE Delaware Avenue is completed.  It is anticipated that the corridor will reopen to traffic in early October, weather permitting. -- updated 8/30/17 

NE 36th Street and the side street connections along the east half of the project between Fourmile Creek and NE Delaware Avenue are completed.  Paving of NE 36th Street along the west half of the project between N Ankeny Boulevard and Fourmile Creek will occur during the middle of August, after the subdrain installation and subbase placement are completed in early August.  The side street connections along the west half will occur in late August.  Paving of the sidewalk and trail throughout the corridor will occur throughout the month of August, with streetlight installation and also the traffic signal installation at the NE Trilein Drive intersection to follow.  The north/south connection at NE 36th Street and NE Briarwood Drive is scheduled to reopen to traffic the week of August 7.  No west/east traffic along NE 36th Street will be permitted until the entire project is fully completed.  It is anticipated that the project will be fully completed no later than Oct. 1, weather permitting. -- updated 8/1/17 

Construction is progressing ahead of schedule.  The paving contractor paved the east half of the NE 36th Street mainline between Fourmile Creek and NE Delaware Avenue in late June / early July.  The paving of the NE Briarwood Drive intersection tie-in will occur during the month of July, along with other side street connections and trail pavement to the east of Fourmile Creek.  The grading contractor is currently performing subgrade preparation, subdrain installation, and subbase placement on the west half of the project.  The paving of the NE 36th Street mainline between N Ankeny Boulevard and Fourmile Creek will likely occur in late July / early August.  For additional details, please refer to the project’s FAQ. -- updated 7/11/17 

Construction is progressing ahead of schedule.  The intersection of NE 36th Street and NE Trilein Drive is now closed to all traffic.  The paving contractor paved the westbound lanes of NE 36th Street between Fourmile Creek and NE Delaware Avenue in late June / early July.  It is anticipated that the eastbound lanes of the east half of the project will be paved the week of July 10, followed by paving of the NE Briarwood Drive intersection tie-in.  The grading contractor will be performing subgrade preparation, subdrain installation, and subbase placement on the west half of the project between N Ankeny Boulevard and Fourmile Creek during the month of July.  For additional details, please refer to the project’s FAQ. -- updated 7/5/17 

Construction is progressing ahead of schedule.  It is anticipated that the north/south intersection of NE Trilein Drive and NE 36th Street will close on Wednesday, July 5.  The paving contractor will be paving the NE 36th Street mainline between Fourmile Creek  and NE Delaware Avenue from Thursday, June 29 to Saturday, July 1st, weather permitting, then will transition into paving the NE Briarwood Drive intersection during the first half of July.  The grading contractor will be performing subgrade preparation, subdrain installation, and subbase placement between N Ankeny Boulevard and Fourmile Creek during the first half of July.  For additional details, please refer to the project’s FAQ. --updated 6/28/17

Construction is progressing ahead of schedule.  It is anticipated that NE 36th Street between N Ankeny Boulevard and NE Delaware Avenue will be reopened to traffic by early Fall.  It is anticipated that the north/south intersection of NE Trilein Drive and NE 36th Street will close in late June, weather permitting.  The contractor is performing subgrade preparation, subdrain installation, and subbase placement during the month of June.  For additional details, please refer to the project’s FAQ. -- updated 6/13/17 

Construction is progressing ahead of schedule.  It is anticipated that NE 36th Street between N Ankeny Boulevard and NE Delaware Avenue will be reopened to traffic by early Fall.  The north/south intersection of NE Briarwood Drive and NE 36th Street will close on Tuesday, May 30, weather permitting.  The north/south intersection of NE Trilein Drive and NE 36th Street will remain open until mid-June.  The contractor is installing storm sewer during the month of May.  For additional details, please refer to the project’s FAQ. -- updated 5/23/17 

Construction is progressing well ahead of schedule.  It is anticipated that NE 36th Street between N Ankeny Boulevard and NE Delaware Avenue will be reopened to traffic by early September.  The north/south intersection of NE Briarwood Drive and NE 36th Street will close on Friday, May 19, weather permitting.  The north/south intersection of NE Trilein Drive and NE 36th Street will remain open until early June.  The contractor will continue to install storm sewer during the month of May.  For additional details, please refer to the project’s FAQ. -- updated 5/16/17 

Construction started in late March 2017 and is anticipated to last the entire construction season.  NE 36th Street from just east of N Ankeny Boulevard / U.S. Highway 69 to just west of NE Delaware Avenue will be closed during this time, with a marked detour on NE 18th Street.  North/South traffic across NE 36th Street at the NE Trilein Drive and NE Briarwood Drive intersections will be maintained until mid to late Summer.  The contractor is installing the storm sewer during the month of May.  For additional details, please refer to the project’s FAQ. -- updated 5/9/17 

Construction started in late March 2017 and is anticipated to last the entire construction season.  NE 36th Street from just east of N Ankeny Boulevard / U.S. Highway 69 to just west of NE Delaware Avenue will be closed during this time, with a marked detour on NE 18th Street.  North/South traffic across NE 36th Street at the NE Trilein Drive and NE Briarwood Drive intersections will be maintained until mid to late Summer.  The contractor is installing the water main during the month of April.  For additional details, please refer to the project’s FAQ. -- updated 4/25/17 

Construction began on March 20, 2017 and is anticipated to be ongoing through the Fall.  NE 36th Street from just east of N Ankeny Boulevard / U.S. Highway 69 to just west of NE Delaware Avenue will be closed during this time.  North/South traffic across NE 36th Street at the NE Trilein Drive and NE Briarwood Drive intersections will be maintained until mid to late Summer.  For additional details, please refer to the project’s FAQ. -- updated 3/23/17 

Construction is expected to begin the week of March 20, 2017.  Construction is anticipated to be ongoing through Fall 2017.  NE 36th Street from just east of N Ankeny Boulevard / U.S. Highway 69 to just west of NE Delaware Avenue will be closed during this time.  For additional details, please refer to the project’s FAQ. - updated 3/14/17 

Construction is scheduled to start in April 2017. -- updated 3/1/17

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer