Project Description

This project includes the grading and paving of SW District Drive from SW Magazine Road to SW Prairie Trail Parkway and SW Merchant Street from SW District Drive to SW Park Square Drive along with associated utility improvements.

The District at Prairie Trail-SW District Dr & SW Merchant St - Project Location Map

Anticipated Start Date

June 5, 2017

Expected Completion Date

November 2017

Progress Update

Mainline paving operations are now complete.  Installation of brick pavers, pavement tie-in work, and street lighting are currently underway.  Motorists are asked to continue using caution for possible turning trucks accessing the site at construction entrances along SW Magazine Rd, SW Westview Dr, and SW Prairie Trail Pkwy. -- updated 9/11/17 

The majority of the utility installation is complete.  Paving operations are now underway.  SW Prairie Trail Parkway will be closed at SW District Drive to accommodate intersection work starting August 23rd for approximately 3 weeks, weather permitting.  Directional signs will be posted for access to the Soybean Association and the FFA Enrichment Center.  See a recent News Release for more detailed information.  Motorists are asked to use caution for possible turning trucks accessing the site at construction entrances along SW Magazine Road, SW Westview Drive, and SW Prairie Trail Parkway. -- updated 8/24/17  

The majority of the water main, storm sewer, and sanitary sewer installation has now been completed.  sub drain work, fiber optic installation, lighting conduit and grading are ongoing.  Motorists are asked to use caution for possible turning trucks accessing the site at construction entrances along SW Magazine Road, SW Westview Drive, and SW Prairie Trail Parkway. -- updated 7/11/17 

Underground work has begun including water main, storm sewer, and sanitary sewer installation.  Initial states of the project will have minimal impact to existing traffic.  Motorists are asked to use caution for possible turning trucks accessing the site at construction entrances along SW Magazine Road, SW Westview Drive, and SW Prairie Trail Parkway. -- updated 6/14/17 

This project is expected to begin the week of June 5.  Initial stages of the project will have minimal impact to existing traffic. -- updated 6/5/17 

This project is currently out to bid. -- updated 4/25/17 

This project is currently in the final design phase. -- updated 4/5/17

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer