Project Description

These projects include various sanitary manhole invert repairs throughout the City and sanitary sewer pipe repair near the Springwood Theater.

Sanitary Sewer Maintenance Program Pipe Repairs - Project Location Map (PDF)

Anticipated Start Date

August 2017

Expected Completion Date

December 2017

Progress Update

Pipe repair project is under construction. The pipe is being installed this week.  Manhole Invert Repairs have begun. The contractor will continue work throughout the fall. Each manhole repair is expected to be completed in one working day. The contractor will provide temporary traffic control as required. -- updated 10/2/17 

Manhole Invert Repairs have begun. The contractor will continue work throughout the fall. Each manhole repair is expected to be completed in one working day. The contractor will provide temporary traffic control as required. Pipe repair is expected to begin in September and will take approximately one week to complete, depending on weather conditions.  -- updated 8/21/17

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer