This project includes pavement reconstruction and minor utility improvements along NW 9th Street from just east of NW Irvinedale Drive to the east connection of NW Park Lane in the City of Ankeny. 

PCC Reconstruction Program - NW 9th St -- project location map

PCC Reconstruction Program - NW 9th St -- detour map

PCC Reconstruction Program - NW 9th St -- Access to Westwood Elementary map

Project Contact

Phone: 515-963-3538

Anticipated Start Date

June 2019

Expected Completion

Early August 2019

Progress Update

 The contractor has been working on the removals, storm sewer, subdrains, earthwork and street subbase.  The contractor is progressing along and is scheduled to pave back the street pavement on July 8, weather dependent.  The road closure and detour will remain in place until the street and driveways can be opened to traffic.  -- updated 7/9/19 

Beginning Monday, June 10, at 9 a.m., NW 9th Street, from NW Irvinedale Drive to the east connection of NW Park Lane, will be closed to traffic. During the closure, motorists should follow the signed detour when traveling through this area of the City. The road closure will remain in place for approximately 2 months until this project is substantially completed and the street and driveways can be opened to traffic. -- updated 6/6/19 

This project was awarded to Halbrook Excavating on March 18, and a preconstruction meeting will be held in May.  This project does include closing NW 9th Street along the project alignment and closure of the adjacent residential driveways and the middle and west entrances into the Westwood Elementary School parking lot.  The east school parking lot entrance will remain open during the construction of this project.  There will be portable message boards put up each direction of NW 9th Street 3 days before the road closure to alert the traveling public.   -- updated 4/23/19 

This project is currently out to bid.

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer