Facility Directory Detail

Project Description

This project includes construction of a PCC trail along old railroad grade and under US Highway 69 by means of a cast-in-place RCB pedestrian tunnel with formliner.  The project also consists of earthwork, PCC street pavement, water main, storm sewer, traffic signal modifications, and other similar items generally located both west and east of South Ankeny Boulevard/US Highway 69, and north of the SW Ordnance Road & South Ankeny Boulevard intersection.

High Trestle Trail Extension-Phase 1 - project location map

High Trestle Trail Extension-Phase 1 - SW Ordnance Road closure - detour map

Project Contact

 Jim Haberichter

Phone: 515-963-3536

Anticipated Start Date

Summer 2019

Expected Completion Date

Fall 2020

Progress Update

The contractor is working on tying into existing water mains and site grading. -- updated 10/22/19 

The contractor is to start trail grading the week of Sept. 16. -- updated 9/11/19 

The contractor should finish the water main boring under South Ankeny Boulevard the week of Sept. 22.  They will then start grading the trail. -- updated 9/5/19 

The contractor will start boring a water main under South Ankeny Boulevard the week of Aug. 26.  They will also be starting grading on the trail. -- updated 8/20/19 

Beginning on Monday, Aug. 5, SW Ordnance Road was closed from south of the entrance to Ankeny High School to SW Ankeny Boulevard.  During the closure, traffic should follow the posted detour using SW Magazine Road and SW Cherry Street.  Pending any weather delays, the road will be re-opened in the afternoon of Friday, Aug. 9.  Following this, the contractor will start boring a water main under South Ankeny Boulevard and continue with storm sewer work. -- updated 8/6/19 

The contractor will begin working on boring a water main under South Ankeny Boulevard the week of July 29.  Beginning on Monday, Aug. 5, SW Ordnance Road will be closed from south of the entrance to Ankeny High School to SW Ankeny Boulevard.  During the closure, traffic should follow the posted detour using SW Magazine Road and SW Cherry Street.  This road closure is needed to install a new culvert under SW Ordnance Road.  Pending any weather delays, the road will be re-opened in the afternoon of Friday, Aug. 9. -- updated 7/30/19 

Beginning on Monday, Aug. 5, SW Ordnance Road will be closed from south of the entrance to Ankeny High School to SW Ankeny Boulevard.  During the closure, traffic should follow the posted detour using SW Magazine Road and SW Cherry Street.  This road closure is needed to install a new culvert under SW Ordnance Road.  Pending any weather delays, the road will be re-opened in the afternoon of Friday, Aug. 9. -- updated 7/24/19

The contractor is scheduled to begin work on July 29.  Water main relocation, storm sewer construction and rough grading will be the contractor's primary work tasks during August. -- updated 7/17/19 

The project was bid on May 14 and awarded on May 20.  Construction is expected to begin this summer.  Additional information will be provided in July when the contractor's schedule is determined. -- updated 6/10/19 

The project was originally bid in February 2019; however, the bids were rejected due to high bid prices.  The project has been repackaged to encourage better bid prices, and it will be re-bid in May 2019. -- updated 4/16/19

Initial bids for this project were rejected due to high bid prices in February 2019.  The project is currently being repackaged to encourage better bid prices and will be re-bid in Spring 2019.

 

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer