Facility Directory Detail

Project Description

The project will install a new traffic signal with minor widening to align NW-NE Georgetown Blvd.

North Ankeny Blvd & NW/NE Georgetown Blvd Traffic Signal - project location map

North Ankeny Blvd & NW/NE Georgetown Blvd Traffic Signal - Detour Map 

Project Contact

Leslie Hart

Phone: 515-963-3548

Anticipated Start Date

June 2019

Expected Completion Date

October 2019

Progress Update

Construction is expected to begin in June 2019, with completion in fall 2019. For the safety of both workers and the public, Georgetown Blvd will be partially closed. Please observe posted detours. -- updated 5/14/19 

The project is out for construction bids, with construction expected to begin in mid-June 2019. -- updated 4/3/19 

Design is completed, and bid-letting is anticipated in late spring.

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer