Facility Directory Detail

Project Description

The project will install a new traffic signal with minor widening to align NW-NE Georgetown Blvd.

North Ankeny Blvd & NW/NE Georgetown Blvd Traffic Signal - project location map

North Ankeny Blvd & NW/NE Georgetown Blvd Traffic Signal - Detour Map 

Project Contact

Leslie Hart

Phone: 515-963-3548

Anticipated Start Date

July 8, 2019

Expected Completion Date

October 2019

Progress Update

Starting Monday July 8: NW Georgetown will be closed between The Gardens of Georgetown and Ankeny Blvd, for approximately three weeks. The signed detour uses NW Ash Drive and NW 18th StreetAfter NW Georgetown is re-opened, NE Georgetown will be closed between Ankeny Blvd and the business accesses (Aldi, Fitness World, etc), for approximately two weeks. The signed detour uses NE Grant Street and NE 18th Street  The West Side and East Side closures are not concurrent. 

Construction is expected to begin in July 2019, with completion in fall 2019. For the safety of both workers and the public, Georgetown Blvd will be partially closed. Please observe posted detours. -- updated 6/25/19 

Construction is expected to begin in June 2019, with completion in fall 2019. For the safety of both workers and the public, Georgetown Blvd will be partially closed. Please observe posted detours. -- updated 5/14/19 

The project is out for construction bids, with construction expected to begin in mid-June 2019. -- updated 4/3/19 

Design is completed, and bid-letting is anticipated in late spring.

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer