Project Description

This project includes the removal and replacement of the existing roadway bridge, reconstruction of the existing roadway and 8’ & 5’ sidewalk connections on NE 54th Street between NE Briarwood Drive and NE Hillcrest Drive in the City of Ankeny.

NE 54th Street Bridge Replacement over Branch of Fourmile Creek - project location map

NE 54th Street Bridge Replacement over Branch of Fourmile Creek - detour map

Project Contact

Jim Haberichter

Phone; 515-963-3536

Anticipated State Date

Spring 2019

Expected Completion Date

September 2019

Progress Update

Final site grading is in progress.  Paving will begin in late August. -- updated 8/20/19 

The contractor is installing storm sewer.  Final site grading will begin after the installation of the storm sewer.  Paving will begin in late August. -- updated 8/6/19 

The contractor begin installing storm sewer on July 29.  Starting the week of August 5, final site grading will begin.  Paving will begin middle to late August. -- updated 7/30/19 

The pavement removal between NE Hillcrest Drive and NE Briarwood Drive and grading started on July 18.  Storm sewer installation should begin the week of July 29.  Street paving will be begin in August. -- updated 7/24/19 

The construction of the bridge is substantially complete.  Pavement removal between NE Hillcrest Drive and NE Briarwood Drive, along with storm sewer installation, will occur in late July, followed by street paving in August.  Once the street paving is completed, the final work on the bridge will commence. -- updated 7/17/19 

The contractor has completed most of the construction work for the bridge structure and their subcontractors have started to come in and start the storm sewer and paving work.  The road closure will continue to remain in place until the project is substantially completed. -- updated 7/9/19 

The contractor has been working on building the bridge structure and is scheduled to pour the bridge deck the week of June 10.  The road closure remains in place until the project is substantially completed. -- updated 6/10/19 

The contractor will be closing down NE 54th Street on Monday, April 22, to begin construction work on this project.  The road closure will be in place until the project is substantially completed in late summer or early fall.  There is a signed detour route to direct the travelling public and local residents around this road closure for the duration of the project.  The contractor will begin with the demolition work and the water main relocation following the closure of the road.  -- updated 4/23/19

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer