 Project Description

This project includes the removal and replacement of the existing trail loop in Crestbruck Park with PCC pavement and removal and replacement of some existing PCC trail along SW State Street between SW 16th Street and SW Magazine Road and along SW Oralabor Road at the pedestrian bridge over the DMACC pond outlet.

Crestbruck Park Recreation Trail Replacement and Misc. Patch Locations - project location map

Project Contact

Matt Grgurich

Phone: 515-963-3549

 Anticipated Start Date

Late July 2019

Expected Completion

Fall 2019

Progress Update

The miscellaneous patch adjacent to SW State Street is complete.  The contractor is now working on the Crestbruck Park trail portion of the project.  -- updated 8/27/19

A preconstruction meeting will be held on July 18.  It is anticipated that work in Crestbruck Park will commence in late July, followed by the removal and replacement of miscellaneous patches adjacent to SW Oralabor Road and SW State Street in early fall.  -- updated 7/17/19 

This project was bid on May 29 and awarded to Shekar Engineering.  A preconstruction meeting will be scheduled with the contractor and a start date will be developed at that time.  -- updated 6/10/19 

This project is currently out to bid. -- 4/23/19

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer