Project Description
Project led by Iowa DOT and DMACC, to widen Oralabor Road to provide dual eastbound left-turn lanes entering the campus.
SW Oralabor Rd & DMACC Blvd Intersection Improvements - project location map
Project Contact
Leslie Hart
Phone: 515-963-3548
Anticipated Start Date
April 2019
Expected Completion Date
Fall 2019
Progress Update
The new traffic signal was turned on Thursday, Oct. 31, with final adjustments and clean-up underway. -- 11/5/19
The new traffic signal is scheduled to be turned on Thursday, Oct. 31, weather pending. -- updated 10/22/19
The new traffic signal is scheduled to be turned on Tuesday Oct. 22, weather pending. -- updated 10/16/19
Installation of new traffic signal poles and equipment is underway. Completion expected in October 2019. -- updated 9/25/19
The intersection was opened to traffic on Aug. 13. Final completion dependent on installation of new traffic signal poles. -- updated 8/20/19
Work to widen Oralabor Road began in May 2019. The intersection will be open prior to DMACC's fall classes. Final completion dependent on delivery of traffic signal poles. -- updated 5/14/19
Work to widen Oralabor Road is expected to begin in mid-May 2019. Final completion is dependent on the delivery of traffic signal poles. -- updated 4/3/19
Preconstruction meeting schedule for mid-March, and work to commence soon after. Final completion dependent on delivery of traffic signal poles.