These operational changes  are reflective of the suggested guidelines provided by the Centers for Disease Control and the Iowa Department of Public Health. The City is committed to protecting its employees and citizens during this pandemic. View additional information on the City of Ankeny response and updates at AnkenyIowa.gov/COVID-19.

    Facility Directory Detail

    Project Description

    This project consists of the construction of SW Des Moines Street from just south of SW Magazine Road to just north of SW Prairie Trail Parkway. One storm water detention basin and three wetlands will also be constructed as part of this project.

    SW Des Moines St Extension - Prairie Trail Pkwy to Magazine Rd -- project location map

    Project Contact

    Jim Haberichter

    Phone: 515-963-3536

    Anticipated Start Date

    Spring 2019

    Expected Completion

    Summer 2020

    Progress Update

    The contractor has completed the street paving and continues to work on the sidewalks and trail paving. -- updated 5/18/20 

    The contractor has completed the mainline paving and continues to pour the intersections, sidewalks, and trail. -- updated 5/5/20 

    The contractor will complete the mainline paving the week of April 27.  They will then start paving the intersections, sidewalk, and trail. -- updated 4/28/20 

    The contactor started subgrade preparation the week of March 30.  Paving will begin the week of April 13. -- updated 4/1/20

    The contractor plans to resume work in early April.  Construction is planned to be completed in summer 2020. -- updated 03/10/20 

    Final grading, paving, and landscaping will be completed in Spring/Summer 2020. -- updated 11/20/19 

    Final grading for paving will begin soon with paving to follow.  Paving will take approximately one month to complete. -- updated 10/22/19 

    Final grading for paving is expected to begin in mid-September with paving to follow.  Paving will take approximately one month to complete. -- updated 8/27/19

    Final grading for paving will start the week of Aug. 19 and paving will begin the week of Sept. 2.  Paving is expected to take approximately one month to complete. -- updated 8/20/19 

    The contractor has completed the underground utility installation.  It is anticipated that a portion of the street paving will commence sometime in late August or early September. -- updated 8/6/19 

    The contractor is continuing to perform underground utility installation along with grading of the site.  It is anticipated that a portion of the street paving will commence sometime in late August or early September. -- updated 7/17/19 

    The contractor is currently working on underground utility work for the project.  -- updated 7/9/19 

    The contractor has been working on grading work and is transitioning into underground utility work for the project. -- updated 6/10/19 

    This project was awarded to Concrete Technologies on April 15.  They plan on starting clearing and grubbing work the week of April 22, and beginning grading and underground operations the following week.   -- updated 4/23/19

     

    Return to full list >>

    Free viewers are required for some of the attached documents.
    They can be downloaded by clicking on the icons below.

    Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer