Facility Directory Detail

Project Description

This project includes vertical rehabilitation of sanitary manholes using a cementitious liner.

2019 Sanitary Sewer Maintenance Program-Manhole Lining Project - project location map

Project Contact

Mitch Wedell

Phone: 515-963-3523

Anticipated Start Date

August 2019

Expected Completion

December 2019

Progress Update

This work is complete and punchlist items should be completed by mid-December. -- updated 11/13/19 

Hydro-Klean awarded the project. This work is complete and we are getting ready to create a punchlist by the middle of October. -- updated 10/9/19 

Hydro-Klean awarded the project and started work the week of August 26. Hydro-Klean is scheduled to resume work the week of September 30. -- updated 9/25/19 

Hydro-Klean awarded the project and started work the week of August 26. Estimated mid to late September completion. -- updated 9/5/19 

Hydro-Klean awarded the project and will start work the week of August 26, 2019. -- updated 8/27/19 

Hydro-Klean was awarded the project and awaiting preconstruction meeting. -- updated 6/10/19

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer