These operational changes  are reflective of the suggested guidelines provided by the Centers for Disease Control and the Iowa Department of Public Health. The City is committed to protecting its employees and citizens during this pandemic. View additional information on the City of Ankeny response and updates at AnkenyIowa.gov/COVID-19.

    Facility Directory Detail

    Project Description

    This project consists of the construction of SE Convenience Boulevard from SE 77th Street to the north approximately 1,200 feet. SE 77th Street will be constructed from the existing street stub west of SE Four Mile Drive to SE Convenience Boulevard. This project will also include a right turn lane on SE Four Mile Drive at SE 77th Street.

    SE Crosswinds Drive RISE - Phase 1 -- project location map

    Project Contact

    Mitch Wedell

    Phone: 515-963-3523

    Anticipated Start Date

    September 2019

    Expected Completion

    Summer 2020

    Progress Update

    Underground utility operations are complete. Subbase preparation has started in early April 2020. Paving operations are anticipated to start by May 2020.  Construction is currently being done so SE Four Mile Drive to install the right turn lane at SE 77th Street. -- updated 4/28/20 

    Underground utility operations are complete. Subbase preparation has started in early April 2020. Paving operations are anticipated to start by May 2020. -- updated 4/7/20 

    Underground utility operations are complete. Subbase preparation and paving operations will start in March/April 2020. -- updated 3/10/20 

    Underground utility operations are complete. This project is officially in winter shutdown. Subbase preparation and paving estimated in the spring of 2020. -- updated 12/4/19 

    Underground utility operations have started and will continue through the fall. Subbase preparation and paving estimated in the spring of 2020. -- updated 10/22/19 

    Sternquist Construction will be the prime contractor for this project. Grading operations have started. Utility operations to start soon. -- updated 9/5/19 

    Sternquist Construction will be the prime contractor for this project. Work will begin the week of Aug. 26.  -- updated 8/20/19

    This project will have a bid opening on August 13, 2019. -- updated 7/24/19

    Return to full list >>

    Free viewers are required for some of the attached documents.
    They can be downloaded by clicking on the icons below.

    Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer