Facility Directory Detail

Project Description

The Phase 2 work consists of four separate Iowa DOT projects being completed simultaneously. 

The work includes the following:
1) Add auxiliary lanes to Northbound and Southbound I-35 between the East 1st St. and Oralabor Rd. interchanges;

2) Widen Southbound I-35 exit ramp at the Oralabor Rd. interchange;

3) Reconstruct Northbound lanes of I-35 from just south of East 1st St. to NE 36th St.;

4) Reconstruct East 1st St. from just west of Fourmile Creek bridge to just east of the Frisk Dr. intersection;

5) Widen approximately 660 ft. of East 1st St. east of Frisk Dr.;

6) Reconstruct Frisk Dr. from just south of East 1st St. to just south of NE 95th Ave.;

7) I-35 Reinforced Concrete Box Culvert Replacement - stage 2; and

8) Traffic Signing

Project Contact

Mark Mueller

Phone: 515-963-3522

Anticipated Start Date

Spring 2019

Expected Completion Date

Fall 2019

Progress Update

Construction is on-going at this time and will continue throughout the entire 2019 construction season.

Please visit the Iowa Department of Transportation’s website for more information regarding this project.

updated 3/12/19

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer