Project Description

Construction of a water booster station and the associated water main needed for the operation of the booster station. The Northwest Booster Station project is generally located along NW Irvinedale Drive, north of NW 18th Street.

Northwest Booster Station project location map

Project Contact

Don Clark

Phone: 515-963-3529

Anticipated Start Date

May 21, 2018

Expected Completion Date

Spring 2019

Progress Update

Construction is wrapping up both inside and out as the contractor will be working on punch list items.   -- updated 6/19/19 

Construction on the facility continues to make progress but a delay in getting power from Mid-American Energy will delay final completion of this project into late May. -- updated 4/16/19 

Construction on the facility continues to make progress and site utilities are installed.  The contractor continues to make progress on the site and it appears to be on track to be completed by the end of April. -- updated 11/27/18 

Construction on the facility continues to make progress and site utilities are also being installed.  The bore under NW 18th Street is now complete and the connection to existing 12” water is all that remains on south side of NW 18th Street.  The contractor will be on site this week to make the connection to the existing water main. -- updated 10/31/18 

Construction on the facility continues to make progress and site utilities are also being installed.  The bore under NW 18th Street is now complete and the connection to existing 12” water is all that remains on south side of NW 18th Street.  There is additional utility work to be completed from the north side of NW 18th Street to the booster station. -- updated 8/28/18 

The boring under NW 18th Street will likely occur this week.  There is no planned street closure for this activity, but we will have a lane down for westbound traffic along NW 18th Street for the first half of this week.  Construction on the facility continues to make progress and site utilities are also being installed. -- updated 8/15/18 

The boring under NW 18th Street will likely occur this week.  There is no planned street closure for this activity.  Construction on the facility continues to make progress and site utilities are also being installed. -- updated 7/24/18 

The boring under NW Irvinedale is complete.  They will be closing NW Irvinedale down to one lane on Monday to fill any voids that occurred during the boring operations.  Flagger will be present directing traffic for today.  Construction on the facility continues to make progress and site utilities are also being installed. -- updated 7/17/18 

Work is underway on the piping within the building as well as the footings for the building.  Exterior utility work will be underway this week to make the connection to the existing water on the north side of the project.  There are no expected road closures with this project. -- updated 6/12/18 

Some construction has begun on this site for the actual facility.  Installation of the 24” water main for this project is expected to begin next week. -- updated 5/30/18 

Due to weather delays, construction is to begin the week of May 21.  -- updated 5/15/18

Construction of the Booster Station will begin on May 7. -- updated 5/2/18 

Construction of the Booster Station will begin on May 1. -- updated 4/11/18

This project is expected to begin construction in April. -- updated 3/1/18 

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer