Facility Directory Detail

Project Description

The SE Creekview Drive Utility Improvements project includes the removal and replacement of six pipe culvert locations and the installation of 12” diameter water main.

SE Creekview Drive Utility Improvements project location map

Project Contact

Adam Lust 

Email: alust@ankenyiowa.gov

Phone: 515-963-3537

Anticipated Start

July 2018

Expected Completion Date

Late May 2019

Progress Update

Water services to the adjacent properties along the west side of SE Creekview Drive are being transferred over from the existing 8” water main to the new 12” water main.  Additional work to be completed in May includes the finish grading and surface restoration along both sides of the corridor and right-of-way. -- updated 5/14/19 

Work began Monday, April 8, with preparation for water main pressure testing followed by bacteria testing.  Once the water main testing passes, the services to the adjacent properties will be transferred over from the existing 8” water main to the new 12” water main.  Additional work to be completed this spring includes the placement of the remaining riprap within the channels and the surface restoration along the corridor and right-of-way using seed and hydromulch. -- updated 4/9/19 

Project is now in winter shutdown.  Work to be completed next spring include riprap placement and  water main pressure testing and disinfection testing, along with the transferring of the water services from the existing main to the new main. -- updated 12/18/19 

Water main installation and pipe culvert replacement are nearly complete.  Work remaining prior to winter shutdown includes pipe apron and riprap placement, along with general cleanup and removal of traffic control along the corridor.  Work to be completed next spring includes water main pressure testing and disinfection testing, along with the transferring of the water services from the existing main to the new main. -- updated 11/27/18 

Water main installation and pipe culvert replacement is ongoing.  There will be time-frames when SE Creekview Drive is restricted to one lane of alternating traffic during the pipe culvert work.  Once the water main passes testing, the water services for the businesses along SE Creekview Drive will be transferred over to the new main.  Businesses will be communicated with in advance of their water service being temporarily shut down during the service transfers. -- updated 9/19/18 

Construction on this project began in late July and will last approximately three months.  Current work operations include the installation of the new water main, followed by service transfers for the adjacent businesses from the old water to the new water main.  Once all water main and water service work is completed, the removal and replacement of the pipe culverts along the corridor will occur.  There will be time-frames when SE Creekview Drive is restricted to one lane of alternating traffic during the pipe culvert work. - updated 7/24/18 

This project has been awarded.  Construction on this project will begin in mid-July. -- updated 5/15/18 

This project is currently in the bidding phase with an award date of May 7, 2018. -- updated 4/2/18 

This project is currently in the design phase.  It is anticipated that the project will have an April bidding phase and be awarded in May. -- updated 3/2/18

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer