This project includes the full depth removal and replacement of PCC street pavement along NW Prairie Ridge Drive from 900 feet west of NW Ash Drive to NW Ash Drive.

PCC Reconstruction Program - NW Prairie Ridge Drive project location map

View the detour map for NW Prairie Ridge Drive Reconstruction -- Starting October 19, 2018

Project Contact

Sarah Okerlund

Email: sokerlund@ankenyiowa.gov

Phone: 515-963-3526

Anticipated Start Date

June 4, 2018

Expected Completion Date

August 2018

Progress Update

This project is substantially complete.  To ensure a quality product, the new pavement will be re-evaluated in Spring prior to finalizing the project. -- updated 11/27/18 

This project is substantially complete.  We are currently working through final punch list items. -- updated 11/6/18 

NW Prairie Ridge Drive is anticipated to close to through traffic from 5 PM Friday October 19 – 6 AM Monday October 22 to accommodate concrete repair work associated with this project.  Motorists will be directed via message boards to use NW 18th Street during the closure.  Access to the Library will be maintained from the west.   -- updated 10/16/18 

NW Prairie Ridge Drive is anticipated to close to through traffic for a single weekend in October to accommodate concrete repair work associated with this project.  In order to minimize public impact, this work will occur after classes are dismissed on Friday until 6 AM the morning classes resume.  Message boards will be displayed along NW Ash Drive and NW State Street 2 days prior to the closure.  Motorists will be directed to use NW 18th Street during the closure.  Access to the Library will be maintained from the west.  Weather conditions play a key role in when this concrete repair work is able to occur therefore more information on the exact dates will be shared once it is known. -- updated 9/25/18 

This project is now substantially complete.  Minor clean-up items and final restoration is expected to be complete by early Fall.  -- updated 8/6/18 

The Contractor will be wrapping up subdrain installation, curb repair, intake repair, and backfill/stabilization this week.  NW Prairie Ridge Drive will remain open to two-way traffic throughout.  Please continue to use caution when in the construction area.  -- updated 7/31/18 

Weather permitting, Prairie Ridge Drive is anticipated to open to two-way traffic by end of day Wednesday July 11.  Construction activities will not occur during SummerFest celebrations, but will resume on Monday July 16.  -- updated 7/10/18

Starting Monday June 4, NW Prairie Ridge Drive will be closed to through traffic between NW State Street and NW Ash Drive to accommodate Phase 1.  This closure is anticipated to reopen on July 11th, prior to Summerfest.  A posted detour (See above) will be in place.  Access to Prairie Ridge Aquatic Center and Kirkendall Public Library will be maintained from the west throughout construction. -- updated 5/30/18 

This project has been awarded.  Work will start when school is dismissed for Summer. -- updated  4/2/18

This project is currently out to bid. -- updated 3/12/18

 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer