Fiber Optic Network Upgrade

Image Unavailable

Project Description

The project includes fiber optic cable, conduit, handholes, and equipment installation and modifications to implement the master fiber optic redundancy needed for both the traffic signal communication network utilized by the Public Works Department and the overall City operations network managed by the Information Technology (IT) Department. The project will place fiber optic cable to implement efficient path-diverse fiber optic rings for primary and secondary communication between traffic signals and between City facilities.

 Anticipated Start Date 

April 2025

Expected Completion Date

Fall 2026

 Progress Update

Conduit installation is completed until spring. The contractor is primarily working on fiber splices and terminations as needed through the winter. -Updated 12/11/25

The contractor is primarily working on fiber splices and terminations in the west half of the City. Conduit installation will begin along NW Ash Drive and NW Prairie Ridge Drive, and is expected to be completed by Thanksgiving.